Case analysis: Optimus Build Limited v Southall and McManus [2020] EWHC 3389 (TCC)

| 16th March 2021
Section 106 of the Housing Grants, Construction and Regeneration Act 1996 (as amended) (“HGCRA”) states that the HGCRA does not apply to contracts where one party is a “residential occupier”, that is a person who lives in or intends to live in the…
Read more...

Case analysis: JSM Construction Limited v Western Power Distribution (West Midlands) PLC [2020] EWHC 3583 (TCC)

| 16th March 2021
Many construction contracts allow for interim or stage payments, and some of those also include a provision for a final account process. The final account process usually involves a gross claim by the payee subject to adjustments for items such as…
Read more...
Photo
Ian Waine

Lockdown – Reflections at the end of week 51

Ian Waine | 12th March 2021
There was an audible sigh of relief in England at the start of this week as children went back to school. Learning and socialising with peer groups recommenced, and parents were relieved of the unenviable challenge of juggling childcare and work…
Read more...

Collateral warranties – what are they are and what to look out for

| 9th March 2021
Collateral warranties are secondary contracts that provide an interested third party with contractual rights against the service provider to a primary contract. Under the collateral warranty, the third party is known as the beneficiary and the…
Read more...